Construction Projects

Current Projects

*This is a list of some of the major projects underway in the Town of Edson. It may not include all of the smaller projects or day to day/short term projects that are currently underway.

For more details on approved capital projects and funding, see our full budget details at www.edson.ca/budget.

Expand Image

UPDATE: March 7th, 2024 PHOTOS

We are excited to share the latest on the Edson and District Library Expansion and Renovation Project, marking progress toward a modern and improved library space for our community. Highlights include interior framing and mechanical rough-ins ongoing and almost complete. The new glulam mass timber has been installed in the expansion space and the focus for the next 3 weeks will be to completing the roof over the expansion area (including new skylights). Once this is complete the remaining efforts will be directed towards drywall and finishing.

We extend our gratitude to our dedicated contractors, project manager, and the community for your unwavering patience and support throughout this journey. Stay tuned for regular updates as we navigate this transformative journey together.

 

UPDATE: December 1st, 2023 PHOTOS

We are excited to share an update on the ongoing renovation and expansion project at the Edson and District Library.

In the past month, we have achieved significant milestones. These include completing mechanical risers along the south window, enhancing the building's infrastructure, and constructing a curb along the grade beam, crucial for structural improvements. Internal work on mechanical and electrical systems has started, setting the stage for enhanced functionality. Additionally, we have poured concrete sidewalks and are well on our way to modernizing the library's interior.

We are genuinely thrilled with the progress and remain dedicated to creating a more functional and inviting space for our community. Stay tuned for more updates as this exciting project continues to take shape!

 

UPDATE: November 6th, 2023 PHOTOS

We are excited to provide you with an update on the progress of the Edson and District Library Expansion Project. We appreciate your ongoing support and patience as we work to enhance our community's library facilities.
 

We are delighted to report that the demolition phase of the project has been successfully completed. This important milestone marks the beginning of our journey toward creating a modern and improved library space that will better serve the needs of our community. 

The project has advanced into the renovation phase following the approval of building permits. Renovation work will primarily occur indoors, making the most of the winter months. 

We thank you for your continued support and understanding during this transition period. The Edson and District Library Expansion Project is designed to enhance the resources and services available to our community, and we can't wait to share the new and improved library with you. 

Stay tuned for more updates as we move closer to achieving our vision for a vibrant and accessible library space. 

On June 29, 2023, Council approved an increase in the Capital Budget for the Library Renovation and Expansion project from $3,000,000 to $3,700,000 with increased town funding of $616,600 to be funded from the Future Civic/Cultural Facility Reserve.

The project funding breakdown is expected to be as follows:

  • Town of Edson - $2,078,600
  • Yellowhead County - $538,000
  • Province - $1,000,000 (CFEP program grant)
  • Library Board - $83,400 (reserves)

Library Expansion Project Presentation - March 23, 2023

NEW TEMPORARY LOCATION ANNOUNCED at 5016 4th Avenue. See the release at www.edson.ca/library.

 

Expand Image

The Town has hired a local contractor to start clearing the trees within the Right of Way of TWP RD 532 between 54th Street South and 63rd Street (Willmore Road).

This process is in preparation for design for road construction.

This new road will provide a second access to the Edson Landfill and the businesses along 54th Street South.

Expand Image

Assessments were required throughout Edson following the substantial flood event this summer to determine how much damage occurred. On June 29th assessments were completed by ISL Engineering with recommendations including upgrading the culverts at 6th avenue.

The report was reviewed by staff and the came to Council requesting funding and approval on July 18th. You can watch the discussion here: https://youtu.be/XDQOiGqK4wk?t=3201

As per the engineering report, the flooding in the community occurred after ground was saturated from previous rains and allowed for little ground absorption. The water ran off, overwhelming streams and storm infrastructure.

Some repairs required include 6th Avenue, the sink hole on 2nd Avenue and other related infrastructure damage.

The 6th avenue repair is large in nature and requires the Town to follow a tendering process under Provincial/Federal Trade regulations. Information on this project can be found below.

The Town of Edson will be proceeding with the 18th Ave Rehabilitation Project from 48th Street going west to the end of the cul-de-sac.

The purpose of this project is to replace the old existing infrastructure.  This includes the watermain, sanitary sewer, storm sewer, roadworks, sidewalk, curb and gutter, asphalt pavement, streetlights, and other associated work.

Parkway Enterprises Ltd. has been contracted by the Town to complete this work. Construction is tentatively scheduled to start the beginning of June 2024, last approximately 120 working days, and be completed by mid October 2024, weather permitting.  

The contractor, along with Engineer, will be in contact with each affected resident prior to construction to provide an update of effected services, including temporary water and access to property.   

During construction, there will be also closure of certain intersections along 48th and 49th Street to through traffic. We ask all residents to follow and obey all posted traffic signs. While we understand that these types of construction projects may cause temporary inconveniences, we assure that every effort will be made to notify the public of any changes, as well as to minimize disruptions to properties in the effected area throughout the duration of the project.

We kindly ask for your cooperation and understanding during the construction period. Your patience and support are greatly appreciated as we work towards creating a better and more resilient community for all.

If you have any questions or concerns about this project, please feel free to contact the Town of Edson’s Infrastructure Department for more information.

Expand Image
New Crack Seal Unit
The new Crack Seal Unit unit is making its way through Edson. This is a new piece of equipment to our transportation department after Council increased the budget for road maintenance and repair. It is used to seal the smaller cracks on the road to stop water penetration. This unit will be used in addition to the Spray Patcher that is used for larger cracks.

Expand Image
Subject to change *Parking lot removed

The project will include rebuilding 5 diamonds at the northeast end of Vision Park, which includes:

  • Landscaping to improve drainage in the lower areas of Vision Park.
  • Construction of two 300-foot diamonds suitable for Slo-Pitch and Baseball.
  • Rebuilding of three diamonds to level the landscape, improve drainage, and upgrade fencing.

Once this work is complete, Vision Park will have 16 operational diamonds, which more than accommodates the needs of Edson Mixed Slo-Pitch and Edson Minor Ball. A park of this size will also attract ball tournaments to the community.

Budget - $1,922,240

Timeline - Work started on September 19, 2022 and is anticipated to continue until August 2023. Grass seed takes a minimum of two full years to grow and establish itself so we anticipate the new ball diamonds will not be operational until the spring 2025.

Background

In 2019 Trans Mountain Pipeline started work installing their new pipeline directly through Vision Park.

Eight of our softball diamonds at Vision Park were either fully or partially located on the Trans Mountain right of away. The work done by Trans Mountain Pipeline resulted in the removal of the playground, 72 full-grown spruce and poplar trees, six ball diamonds, and partially impacted two other diamonds.

Trans Mountain must return all sites on their right of way to their original condition after the excavation and construction, however, Trans Mountain and the Town of Edson jointly identified that it might be in the Town’s best interest to rebuild the affected ball diamonds and other structures rather than Trans Mountain. The Town of Edson rebuilding the diamonds (with financial contributions from Trans Mountain) would ensure the Town of Edson could rebuild them in alignment with the new Vision Park Revitalization Plan.

The Town of Edson Parks Department worked with EDS Group to build a revitalization plan for Vision Park in June 2020. A draft plan was presented to Council on October 27, 2020. The plan included a phased approach, with phase one being rebuilding the diamonds removed by Trans Mountain. Unfortunately, tenders came in far over budget and the plan was scaled back in consultation with user groups.

Upcoming Projects

CONTRACT AWARDED

We are delighted to announce that, following a thorough evaluation process, the Town of Edson has awarded the contract for the 10th Ave and 54th Street Utility Upgrade (Sanitary System Upgrade) to GS Holdings Company Ltd. O/A GS Construction for $ 3,525,600.00 (excluding GST). This decision comes after careful consideration of various proposals and assessments of qualifications and experience.

The 10th Ave and 54th Street Utility Upgrade holds significant importance in enhancing the in enhancing the sanitary sewer infrastructure in our community. We are confident that the expertise and dedication of GS Holdings Company Ltd. will ensure the successful completion of this project, benefiting our residents for years to come.

GS Holdings Company Ltd. has demonstrated a strong commitment to quality, safety, and timely delivery in their past projects, aligning closely with our Town's values and objectives for this endeavor. We are excited to collaborate with them to bring this vision to reality.

Project includes upgrades on Wase Creek on 1st avenue between Highway 16 overpass and 48th Street to mitigate flooding and drainage issues.

Budget - 90% grant funded. More details to come.

Timeline - Design activities are started and a land agent is currently working on the file to secure rights of access for geotechnical investigations and future work plans.

Long Term Projects

The Town of Edson and Yellowhead County are embarking on a historic joint project.

Following many years of public input and facility studies, our communities have come together to start work on a new Multi-Use Recreational Facility.

After initial plans for the Hillendale site came in over budget, the project team was tasked with looking at alternatives which can achieve similar results, but within the approved $70 million budget.

Work is now underway on a condition assessment for major building components and complete a conceptual design and cost estimate at the current site of the Edson and District Leisure Centre. The updated plan is expected to be complete by December 2022.

More details can be found at www.edson.ca/facility.

Completed Projects

Expand Image
This project included replacement and upsizing the culverts under 6th Avenue (east of 48th Street), repair /replacement of damaged underground infrastructure, rebuilding the damaged portion of 6th Avenue, and installing new pavement and sidewalks.
 
ISL Engineering and Land Services Ltd. was been awarded the Design and Construction Management for the project. Construction of this project is being done by Kaon Infrastructure Ltd.
 

UPDATE September 29, 2023

The scope of work for this project was expanded to include a replacement of 56 meters of leaking Sanitary Sewer line and one manhole that is in a poor condition.

 

UPDATE November, 2023

6th Avenue is now open to the public, with the contractor returning in the spring to lay asphalt.

Expand Image
Conceptual Drawing

Project is to install a new water treatment plant (WTP) and public use facility at Vision Park.

In 2020, the Town undertook facility design at Vision Park to make use of an existing licensed water well that requires treatment to meet potable water quality standards. The Vision Park Water Treatment Plant design includes a process area and a separated area with washrooms and meeting space for use by the public within the park.

Budget - $2,274,660

More details can be found in the agenda from the May 25th, 2021 Committee of the Whole Meeting and the June 1st, 2021 Council Meeting.

Expand Image

From August 10, 2023, to approximately August 18, the Town of Edson Public Works will be performing road maintenance on 1st Avenue (48th Street to 50th Street). The primary scope of work will be the removal of all existing asphalt, repairing potholes, and re-gravelling. The affected roadways will be available for local traffic only, please expect delays and temporary closures during this period.

 

Update August 30, 2023

This project is now complete!

Expand Image
Demolition and removal of the bridge in the Edson Lions Park Campground is underway and expected to be complete by Sunday, November 26th, 2023.
 
The bridge is being removed for safety reasons.
 
Please keep out of the campground while work is underway and avoid that section of the trail system until removal is complete.

Expand Image

A new facility has replaced the old outdoor arena structure in Glenwood Park and provide year-round recreational opportunities for residents. The structure is a cement base which lowers the staff resource implication in the winter as the arena will be much easier to flood. It may also allow earlier flooding of the ice surface, potentially leading to a longer winter skating season.

Considering that the facility will now provide year-round recreational opportunities, such as basketball and pickle ball in the summer months, greater usage of the park is anticipated.

Budget - $435,000 (75% grant funded)

Timeline - Project is complete and the new facility is ready for use!

More details can be found in the agenda from the March 15th, 2022 Council Meeting.

Expand Image

New pedestrian crosswalk lights have been installed at 4th Avenue and 46th street. This project consists of a flashing crosswalk sign mounted on a cantilever style pole, side mounted flashing indicator signals, and pedestrian push buttons and crosswalk signage on both sides of roadway.

 Update August 4th, 2023

The north pedestrian light is working but the south signals are still malfunctioning. A new signal system has been ordered and will be installed upon delivery. The signals will be wrapped out of order until they repaired, please be cautious crossing 2nd Ave (Hwy 16) and 46 St intersection.

Budget - Approximately $150,000.

Timeline - Project is now complete!