New Weyerhauser Trail Connection

New Weyerhauser Trail Connection

Project Start Date

Spring 2025 - site survey

Expected Completion

Phase updates coming soon

Project Budget

$376,000

Funded by

Revenue Sharing Agreement ($250,000) / Grants ($126.000)

Progress continues on the new Weyerhaeuser Trail connection:

Crossing Agreements: Applications for the ATCO Gas and Telus line crossings have been submitted and are currently awaiting approval. These approvals are required before hydrovac work can begin.

Wetland Assessment: The environmental assessment is scheduled for completion by late May.

Historical Resources Act (HRA): The HRA process is now underway.

Site Survey: The trail site survey will be completed once snow has fully melted and ground conditions allow.

Stay tuned for more updates as we move into the next phase of development.