New Weyerhauser Trail Connection

Progress continues on the new Weyerhaeuser Trail connection:
Crossing Agreements: Applications for the ATCO Gas and Telus line crossings have been submitted and are currently awaiting approval. These approvals are required before hydrovac work can begin.
Wetland Assessment: The environmental assessment is scheduled for completion by late May.
Historical Resources Act (HRA): The HRA process is now underway.
Site Survey: The trail site survey will be completed once snow has fully melted and ground conditions allow.
Stay tuned for more updates as we move into the next phase of development.