Vision Park Redevelopment

Vision Park Redevelopment

Project Start Date

Spring 2025

Expected Completion

Phase 2 completion fall 2025

2025 Budget

$1,100,000

Funded by

Vision Park Reserve

After consulting with Slo-Pitch and Baseball Users over the winter, a consensus has been reached regarding the 2025 construction plan.

Diamonds 1, 2, 3, and 4 will see the fencing and dugouts installed this summer, and a landscaping company will be retained to repair and maintain the new turf in these diamonds ensuring they will be open and ready to use for the 2026 season.

The second focus for 2025 will be completing upgrades to Diamond #9 in preparation for the Baseball Provincial Tournament, which will be hosted by Edson from July 18-20. The enhancements will include extending the infield and replacing some of the shale with sod, as well as installating a regulation pitcher's mound.

Once the 2025 projects are complete, the Town, in consultation with the User Groups, will re-evaluate a potential 2026 project, considering the best enhancements possible with the remaining funding for this project