B1 Sanitary Upgrade Project Schedule
Posted on
UPDATE - PARKING
Please note that the no-parking signs got a little ahead of themselves. While the no-parking signs are up, construction on this project is not starting until Monday. Parking in the area IS ALLOWED until Monday morning. We apologize for the confusion.
___
We would like to inform residents and stakeholders that work on the B1 Project is scheduled to begin early next week(June 2nd). In preparation, the contractor will begin installing signage in the project area this weekend (May 31st – June 1st).
The B1 Project will be carried out in two phases:
Phase 1:
- 10 Avenue, 52 Street, 12 Avenue / 54 Street
Construction for Phase 1 will commence early next week.
Phase 2:
- 13 Avenue / 54 Street
Work on Phase 2 is anticipated to begin in late July or early August. More precise dates will be communicated as the project progresses and timelines are confirmed.
In addition, please note that 53 Street will be used as a laydown area for the contractor’s equipment and materials throughout the duration of the project.
We are committed to keeping the community informed and will continue to provide updates as work advances. We thank you for your patience and cooperation as we work to improve local infrastructure.
If you have any concerns, please do not hesitate to contact Dillon Jones (PME Superintendent) (582)643-7283.
Your cooperation is greatly appreciated.